Using relevant programmes and official records at the point of the change, NPAC was instructed to support an MEP client with a prospective analysis for various scope change delays.
All work was carried out to NEC3 ECC Option A & C requirements.
This was a long-term commission whereby the change was delivered from blank canvas to financial implementation.

Using relevant programmes and official records at the point of the change(s), NPAC was instructed to support an MEP client with a prospective analysis for various scope changes and the corresponding delays. This involved a 'Global Reset Agreement' for the entire delivery schedule, which included FEED, Detailed Design, Manufacturing, Supply Chains, Install and Commissioning. NPAC also supported the Narrative Paper from a commercial standpoint and provided a checking facility for commercial deliverables on the project.
All work was carried out to NEC3 ECC Option A & C requirements.
This was a long-term commission whereby the change was delivered from blank canvas to financial implementation.